Assigning Uncategorized Resources to a Cost Center
Steps for moving unassigned resources into an existing or a new Workload Manager cost center.
-
Verify that you are logged in to the Workload Manager web UI.
-
In a supported browser, log into the Cloudera Data Platform.
The CDP Public Cloud web interface landing page opens.
- From the Your Enterprise Data Cloud landing page, select the Workload Manager tile.
-
In a supported browser, log into the Cloudera Data Platform.
- From the Workload Manager Navigation side-bar, select Chargeback.
- In the Chargeback page, select a cost center and then a cluster.
-
From the Overview tab, scroll down and click inside the
Uncategorized section.
The Uncategorized page opens.
- Select the required uncategorised resource tab.
-
From either the Pools, Users, or
Clusters page, select the check boxes of the
resources you require for your cost center.
The Assign Cost Center button becomes visible.
- Click Assign Cost Center.
-
From the Select Cost Center list, do one of the
following:
- To add the uncategorized resource/s in a new cost center, select New Cost Center and then click Create a new cost center.
- To add the uncategorized resource/s in an existing cost center, select an existing cost center and then click Assign to Cost Center.
- (Optional) Repeat steps 4-8 until all your uncategorized resources are placed in your Workload Manager cost centers.