Steps for moving unassigned resources into an existing or a new Workload XM cost center.
Describes how to locate and move uncategorized resources into an existing or a new
Workload XM cost center.
-
In a supported browser, log in to Workload XM on-premises.
-
From the Workload XM Navigation side-bar, select
Chargeback.
-
In the Chargeback page, select a cost center and then a cluster.
-
From the Overview tab, scroll down and click inside the
Uncategorized section.
The Uncategorized page opens.
-
Select the required uncategorised resource tab.
-
From either the Pools, Users, or
Clusters page, select the check boxes of the
resources you require for your cost center.
The Assign Cost Center button becomes visible.
-
Click Assign Cost Center.
-
From the Select Cost Center list, do one of the
following:
- To add the uncategorized resource/s in a new cost center, select
New Cost Center and then click
Create a new cost center.
- To add the uncategorized resource/s in an existing cost center, select
an existing cost center and then click Assign to Cost
Center.
-
(Optional) Repeat steps 4-8 until all your uncategorized resources are placed
in your Workload XM cost centers.